Construction of 1x3x2 RCC Box Culvert in km. 3 at Atatuta Samnapur Thakuran Sirkauli Link Road Under SR Yojna
Estimated Value
₹26.53 Lakh
PercentageEMD Guarantee
₹2.65 Lakh
Exemption AllowedTender Fee
₹944
PayableWork Period
60 Days
Awarded: SHIVAM CONSTRUCTION 19 Jan 2026
BiddingTech OpeningFinancial OpeningAOC Award
Contractor Tender Intelligence
Pro FeatureUnlock should you bid, how much to bid, and who will bid.
Tender Details
ID: 2025_CEUFZ_1098403_2 Percentage
Work Description
Description
Construction of 1x3x2 RCC Box Culvert in km. 3 at Atatuta Samnapur Thakuran Sirkauli Link Road Under SR Yojna
Key dates
Published12 Dec 2025, 12:00 pm
Bid due19 Jan 2026, 12:00 pm
Bid opening19 Jan 2026
Documents until19 Jan 2026
Bidders & evaluation
✓ 1. e-Publishing
12 Dec 2025, 12:00 pm
✓ 2. Bid Submission
Closed 19 Jan 2026, 12:00 pm
✓ 3. Tech Opening
6 bids recorded • 1 qualified
✓ 4. Financial Opening
6 ranked • L1 ranked
✓5. Award (AOC)
SHIVAM CONSTRUCTION
Financial Evaluation & L1 Contractor Ranking
| Rank | Contractor / Firm Name | Quoted Bid (₹) | Variance vs Estimate | Portal Status | Committee Remarks | Action |
|---|---|---|---|---|---|---|
| L1 | SHIVAM CONSTRUCTION↗ Bid ID: 5813385•Submitted: 19-Jan-2026 10:31 AM | ₹18.42 Lakhs | -30.58% ₹-8,11,305 | Accepted-AOC | Lowest Bidder | Profile ↗ |
| L2 | RANJANA PANDEY↗ Bid ID: 5748983•Submitted: 26-Dec-2025 11:01 AM | ₹19.19 Lakhs | -27.66% ₹-7,33,787.71 | Rejected-Finance | - | Profile ↗ |
| L3 | PAL & SONS↗ Bid ID: 5812452•Submitted: 18-Jan-2026 11:26 PM | ₹19.77 Lakhs | -25.47% ₹-6,75,781.56 | Rejected-Finance | - | Profile ↗ |
| L4 | Acme Construction Company↗ Bid ID: 5749296•Submitted: 12-Jan-2026 06:46 PM | ₹20.43 Lakhs | -22.98% ₹-6,09,601.83 | Rejected-Finance | - | Profile ↗ |
| L5 | Sukhmani Traders↗ Bid ID: 5812995•Submitted: 19-Jan-2026 12:56 AM | ₹21.29 Lakhs | -19.76% ₹-5,24,174.6 | Rejected-Finance | - | Profile ↗ |
| L6 | SATISH KUMAR↗ Bid ID: 5811554•Submitted: 17-Jan-2026 07:31 PM | ₹24.32 Lakhs | -8.34% ₹-2,21,224.35 | Rejected-Finance | - | Profile ↗ |
Technical Cover Scrutiny Results (6)
Checked by the department's scrutiny committee
| # | Bid ID | Contractor Name | Submitted Date | Technical Status | Disqualification / Remarks | Portal Status | Profile |
|---|---|---|---|---|---|---|---|
| 1 | 5749296 | Acme Construction Company | 12-Jan-2026 06:46 PM | ✕ DISQUALIFIED | REJECTED DUE TO HIGHEST RATE QUOTED | Rejected-Finance | Dossier ↗ |
| 2 | 5812452 | PAL & SONS | 18-Jan-2026 11:26 PM | ✕ DISQUALIFIED | REJECTED DUE TO HIGHEST RATE QUOTED | Rejected-Finance | Dossier ↗ |
| 3 | 5748983 | RANJANA PANDEY | 26-Dec-2025 11:01 AM | ✕ DISQUALIFIED | REJECTED DUE TO HIGHEST RATE QUOTED | Rejected-Finance | Dossier ↗ |
| 4 | 5811554 | SATISH KUMAR | 17-Jan-2026 07:31 PM | ✕ DISQUALIFIED | REJECTED DUE TO HIGHEST RATE QUOTED | Rejected-Finance | Dossier ↗ |
| 5 | 5813385 | SHIVAM CONSTRUCTION | 19-Jan-2026 10:31 AM | ✓ QUALIFIED | Credentials verified per NIT specifications | Accepted-AOC | Dossier ↗ |
| 6 | 5812995 | Sukhmani Traders | 19-Jan-2026 12:56 AM | ✕ DISQUALIFIED | REJECTED DUE TO HIGHEST RATE QUOTED | Rejected-Finance | Dossier ↗ |
Documents & BOQ
Members Only
Member Feature • Free Registration
Tender Documents & Itemised BOQ Protected
Sign in free to download the notice, bidding documents and BOQ.
✓Original BOQ (.xls)
✓Official NIT & SBD
✓Extracted Criteria
Location
BARABANKI 225001